In 4D planning, this refers to the ability to incorporate and simulate schedules and construction processes into a model. This provides a better basis for alternative planning and construction processes, better control over construction progress, faster billing, and a clearer overview of on-site operations, thereby improving the coordination of site setup and logistics.

Option 1: Using MS Project

  • Create processes

Option 2: using a CSV file

  • Select template file: "Schedule(Excel)_TEMPLATE.xlsx"
  • Create activity types (predefined; additional types can be added)
Activity Type/Process TypeWhat happens to the element
ConstructionCreated elements
Abortcancelled elements
TemporaryTemporary elements
  • Each process should be on a separate line (e.g., "Build ground floor walls, replace existing ground floor doors," etc.)
  • Specify dates
  • Save as .csv
  • Open with a text editor
  • Replace all ";" with "," (under Edit -> Replace)
  •  Save as .csv

Create and define Revit parameters

If the required 4D_... parameters have not already been created and defined in the template, they can be loaded into the project from the shared parameter list and assigned to the appropriate categories.

Nummer.png
Fig. 1

NWC Export Settings

Navisworks.png
Fig. 2

Open NWC file

  • Open Navisworks
  • Open the Timeliner, Animator, and Selection Tree windows.

Navisworks_Ansichten.png
Fig. 3
  • Check whether the parameter 4D_Number is present in the selection structure under "Component".

4D_Nummer.png
Fig. 4

Import/synchronize schedule

Timeliner.png
Fig. 5
  • Settings for CSV Import

CSV_Import.png
Fig. 6
  • Clicking "Update" creates the data as activities in Navisworks.

Timeliner2.png
Fig. 7

The activity hierarchy must be recreated the first time; after that, it will only be synchronized.

Datenquelle.png
Fig. 8
  • Check whether a schedule has been created.

Kontrolle.png
Fig. 9

Automatic mapping

Timeliner3.png
Fig. 10

A. Automatically map the display ID and process number -> Apply rule.

ID.png
Fig. 11

B. Select columns

Timeliner4.png
Fig. 12
  • Check whether a selection is assigned to each process

Timeliner6.png
Fig. 13

Simulate and export

  • Check whether the simulation is correct.

Timeliner7.png
Fig. 14

Animation (Optional)

  • Open Animator
  • Create each process to be simulated
  • Create a keyframe at 0:00 and 0:05.00. A diamond will then appear at the beginning and end, respectively.

Animator.png
Fig. 15
  • Click on the respective start screen images and then click Edit.

Animator2.png
Fig. 16
  • Change position Z to 100,000 m

Schluesselbild.png
Fig. 17